Crews worked quickly through the mist this morning and have nearly half of the roof decking on already! They are anticipating completing the roof decking today. They will be back on Monday to finish up the entrance/lobby steel supports, truss, and decking. Again, great progress!!
Wednesday, December 23, 2015
Tuesday, December 22, 2015
Friday, December 18, 2015
Thursday, December 17, 2015
Crews finished up more of the exterior wrap and wall structure today. While other crews worked on the bathroom plumbing and central wall. Roof trusses are to be delivered early this next week and the roof is anticipated to be completed by the second week of January!! What a blessing this project has been so far! Thank God for a smooth process so far with no major glitches to set us back. Continue to pray for the safety of the workers, the campaign, and our church and school mission. Praise God from whom ALL blessings flow!
Tuesday, December 15, 2015
Crews made some more progress today by finishing up some exterior wall boards and putting some of the finishing touches on the block work around the windows and beams. Plumbing in the bathroom was also worked with installation of some supply and waste lines. They continue to have good weather to work in this typical Michigan December!
Sunday, December 13, 2015
The concrete floor was finished being poured by 8:30. They were still drying and finishing it late into the evening hours! Crews were cutting seams too! Insulation and exterior wood framing was installed as well. The 5/6th Graders stole an opportunity to get a quick photograph with the progress too!
Thursday, December 10, 2015
Crews were here early this morning, before 5:00 A.M. pouring the concrete floor. It was amazing to see how fast and coordinated this part of the process went. Some of the pictures are fuzzy because it's dark outside, but hopefully you get an idea as to what is going on. At one point in time round 5:30, there were as many as 5 concrete trucks here on site. The floor will be finished this morning and curing for the next couple of days. The weather has been obedient for this work to take place, which shows that God continues to bless this project. Keep checking in to see more updates!
| Followed the cement trucks this morning at 5:30 A.M. These weren't even the first ones either! |
Wednesday, December 9, 2015
Great news!! Not only have the crews finished all of the exterior walls and are almost complete with the interior block walls, but they have notified us that they will be pouring our concrete floor tomorrow morning! This is a major step in the process which will allow for more work to be done in the coming months and make it easier to complete interior work. They leveled the ground inside and laid down the vapor barrier, hung some lights for working tomorrow morning early in the dark! Crews are anticipated to start working at 5:30 A.M.!! We have been truly blessed throughout this construction process with great weather, expert crews, and fantastic progress! Continue to pray for more positive news to come! Enjoy the photos! REMINDER: Please stay away from the construction site as it is still not safe. Viewing from the interior windows is best!
Tuesday, December 8, 2015
Saturday, December 5, 2015
Wednesday, December 2, 2015
Monday, November 30, 2015
Wednesday, November 25, 2015
Tuesday, November 24, 2015
Monday, November 23, 2015
With winter setting in here in Northern Michigan, the construction plans were reassessed and work adjusted. The concrete floor will be poured when there are some consecutive days of 40+ weather. In the meantime, we are moving forward with block laying for the walls. Then the roof will be installed so that the structure can be enclosed for the bulk of winter allowing for progress to take place inside. Thankful that these guys don't mind the cold!
Wednesday, November 11, 2015
Tuesday, November 10, 2015
Wednesday, November 4, 2015
Plumbing drainage has been finished and approved! Little green stickers are always a welcome sight on a construction project! A base row of cinder blocks will be laid next and the ever important compacting process follows. Next week, the concrete pad will be poured if all goes as planned. Continue to pray for the process and construction crews!
Tuesday, November 3, 2015
Friday, October 30, 2015
Tuesday, October 27, 2015
Monday, October 26, 2015
Subscribe to:
Posts (Atom)






