Wednesday, December 23, 2015

Crews worked quickly through the mist this morning and have nearly half of the roof decking on already! They are anticipating completing the roof decking today. They will be back on Monday to finish up the entrance/lobby steel supports, truss, and decking. Again, great progress!!

Tuesday, December 22, 2015


They're they go! Roof trusses are flying up today!  The progress report from our General Contractor was very positive with most everything is on schedule or ahead of schedule. The weather is been critical in the progress so far and the forecast is looking good the next couple of days. Crews are hoping to have the roof decking on sometime in the next couple of days and maybe early next week. Interior work in the narthex will begin here over break with new water lines, electrical conduit, and networking conduits run. A temporary wall will be installed in the future school entrance to allow crews to demolish the exterior wall later on and not interfere with school or church functions. Please be aware of that change to the narthex. All in all, we can feel very blessed with the progress that has been made! This kind of progress is a truly wonderful CHRISTmas present! Continue to check back in for updates and pictures of the progress over break!

Friday, December 18, 2015

Lookie here...what are those you ask? Those are trusses and roof decking. Crews will be installing trusses on Monday, weather depending. Again...our progress has been blessed!! Keep checking back for more information and spread the word about the blog so that others can keep clued in as well!

Thursday, December 17, 2015

Crews finished up more of the exterior wrap and wall structure today. While other crews worked on the bathroom plumbing and central wall. Roof trusses are to be delivered early this next week and the roof is anticipated to be completed by the second week of January!! What a blessing this project has been so far! Thank God for a smooth process so far with no major glitches to set us back. Continue to pray for the safety of the workers, the campaign, and our church and school mission. Praise God from whom ALL blessings flow!

Tuesday, December 15, 2015

Crews made some more progress today by finishing up some exterior wall boards and putting some of the finishing touches on the block work around the windows and beams. Plumbing in the bathroom was also worked with installation of some supply and waste lines. They continue to have good weather to work in this typical Michigan December!

Sunday, December 13, 2015

The concrete floor was finished being poured by 8:30. They were still drying and finishing it late into the evening hours! Crews were cutting seams too! Insulation and exterior wood framing was installed as well.  The 5/6th Graders stole an opportunity to get a quick photograph with the progress too!

Thursday, December 10, 2015

Crews were here early this morning, before 5:00 A.M. pouring the concrete floor. It was amazing to see how fast and coordinated this part of the process went. Some of the pictures are fuzzy because it's dark outside, but hopefully you get an idea as to what is going on. At one point in time round 5:30, there were as many as 5 concrete trucks here on site. The floor will be finished this morning and curing for the next couple of days. The weather has been obedient for this work to take place, which shows that God continues to bless this project. Keep checking in to see more updates!
Followed the cement trucks this morning at 5:30 A.M. These weren't even the first ones either!

Wednesday, December 9, 2015

Great news!! Not only have the crews finished all of the exterior walls and are almost complete with the interior block walls, but they have notified us that they will be pouring our concrete floor tomorrow morning! This is a major step in the process which will allow for more work to be done in the coming months and make it easier to complete interior work. They leveled the ground inside and laid down the vapor barrier, hung some lights for working tomorrow morning early in the dark! Crews are anticipated to start working at 5:30 A.M.!! We have been truly blessed throughout this construction process with great weather, expert crews, and fantastic progress! Continue to pray for more positive news to come! Enjoy the photos! REMINDER: Please stay away from the construction site as it is still not safe. Viewing from the interior windows is best!

Tuesday, December 8, 2015

Progress continues to go quite well. Crews are almost finished with the block walls because the weather has been quite favorable for working.

Saturday, December 5, 2015

Crews finished up the west wall and part of the south wall yesterday. This weather has really made for great progress. Continue to pray for the construction process and for the campaign.

Wednesday, December 2, 2015

Masonry crews made great progress today with block walls. They anticipate having the walls finished by the end of this week or early next week. The roof decking is anticipated to be delivered mid-December as well. Praise God for great weather and great crews!