Thursday, December 10, 2015

Crews were here early this morning, before 5:00 A.M. pouring the concrete floor. It was amazing to see how fast and coordinated this part of the process went. Some of the pictures are fuzzy because it's dark outside, but hopefully you get an idea as to what is going on. At one point in time round 5:30, there were as many as 5 concrete trucks here on site. The floor will be finished this morning and curing for the next couple of days. The weather has been obedient for this work to take place, which shows that God continues to bless this project. Keep checking in to see more updates!
Followed the cement trucks this morning at 5:30 A.M. These weren't even the first ones either!

Wednesday, December 9, 2015

Great news!! Not only have the crews finished all of the exterior walls and are almost complete with the interior block walls, but they have notified us that they will be pouring our concrete floor tomorrow morning! This is a major step in the process which will allow for more work to be done in the coming months and make it easier to complete interior work. They leveled the ground inside and laid down the vapor barrier, hung some lights for working tomorrow morning early in the dark! Crews are anticipated to start working at 5:30 A.M.!! We have been truly blessed throughout this construction process with great weather, expert crews, and fantastic progress! Continue to pray for more positive news to come! Enjoy the photos! REMINDER: Please stay away from the construction site as it is still not safe. Viewing from the interior windows is best!

Tuesday, December 8, 2015

Progress continues to go quite well. Crews are almost finished with the block walls because the weather has been quite favorable for working.

Saturday, December 5, 2015

Crews finished up the west wall and part of the south wall yesterday. This weather has really made for great progress. Continue to pray for the construction process and for the campaign.

Wednesday, December 2, 2015

Masonry crews made great progress today with block walls. They anticipate having the walls finished by the end of this week or early next week. The roof decking is anticipated to be delivered mid-December as well. Praise God for great weather and great crews!

Monday, November 30, 2015

The weather has been favorable for this time of year for block laying. The walls continue to rise and we start to get more of a perspective of size and shape of our new school.

Wednesday, November 25, 2015

The weather has been cooperating allowing for more progress on the walls. Bathroom plumbing is nearing completion, electrical outlets are being installed as well. The center bearing wall is on the rise!