The two week lull has gradually come to an end with a few items being worked on here at the new school. The major work happening was the installation of the 4" gas supply line running to the new school. Outside our window, the process seemed precarious! Lifting a 15-20' piece of pipe that is strapped to a lift seems risky to me, but the crews did a great job and got it installed without any glitches. They are now working on the gas line on the roof today.