Friday, May 6, 2016

The paint crew has been working long hours into the evening to finish painting as quickly as possible. The second coat of paint and the accent walls will be finished today. All paint should be finished by next week. Lockers are being delivered and installed within the next week or so, with all of the flooring scheduled to be installed simultaneously or shortly thereafter. The ceilings are being hung starting Monday as well. Outside, the siding is 95% done with the remaining amount to be finished up either day or early next week. Everything is starting to come together and looks great. Enjoy the pictures!